Abstract
The High Rate Water Treatment Plant (HR-WTP) system, which is inexpensive, effective and efficient, has been developed to reduce the common operational problems, and also as an alternative for the development of water treatment plant systems capacity in Indonesia.
Implementation of HR-WTP system in up-rating of the Dekeng-WTP system at PDAM Kota Bogor proved successful in increasing the plant capacity from its original of 500 Lps to more than 1200 Lps. The performance of the WTP system was also significantly improved from poor performance to very good performance.
The investment cost for up-rating proved competitive when compared to alternatively constructing a new WTP system with an equivalent capacity and performance. Application of HR-WTP systems for the development of WTP system in Indonesia, i.e. rehabilitation, up-grading, and up-rating, as well as construction of a new WTP system, is expected to bring technical, financial, and economic benefits. This new approach might be an innovative solution to the challenge of Millennium Development Goals in Water Supply Sector in Indonesia, where an additional capacity of ca 150,000 Lps should be developed within a 15 years period with an estimated budget of US $1.5 billions. This budget might be reduced to less than 50% through the application of the HR-WTP system.
Implementation of HR-WTP system in up-rating of the Dekeng-WTP system at PDAM Kota Bogor proved successful in increasing the plant capacity from its original of 500 Lps to more than 1200 Lps. The performance of the WTP system was also significantly improved from poor performance to very good performance.
The investment cost for up-rating proved competitive when compared to alternatively constructing a new WTP system with an equivalent capacity and performance. Application of HR-WTP systems for the development of WTP system in Indonesia, i.e. rehabilitation, up-grading, and up-rating, as well as construction of a new WTP system, is expected to bring technical, financial, and economic benefits. This new approach might be an innovative solution to the challenge of Millennium Development Goals in Water Supply Sector in Indonesia, where an additional capacity of ca 150,000 Lps should be developed within a 15 years period with an estimated budget of US $1.5 billions. This budget might be reduced to less than 50% through the application of the HR-WTP system.
Keywords
loading rate
filtration rate
conventional system
high rate system
Article Details
License
Authors who publish with this journal agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access).