Main Article Content
Abstract
The increasingly high development in Indonesia has spurred the number of construction service companies to increase. On the other hand, the increase in the growth of construction service companies has not been accompanied by a good atmosphere of construction implementation. As a result, delays in completing work have become commonplace in construction projects in Indonesia, the eastern part, and especially Papua. This research investigated the factors causing delays in completing construction work in Papua Province, especially in Merauke Regency. Questionnaires were distributed to contractors registered as members of GAPEKSINDO and domiciled in the Merauke district. The purposive sampling technique took the number of samples. The data analysis in this research used a Non-Parametric Statistical Test with Kendall's W analysis using SPSS 25.0 for the Windows program. The seven main factors that cause construction project delays are related to consultants. The test results show that the main factor of delay in construction projects in the Merauke Regency is the labor factor, with a mean rank value of 2.56. Factors that do not affect construction delays are other factors with a mean rank value of 5.28.
Keywords
Article Details
Under the following term:
-
Attribution — You must give appropriate credit, provide a link to the license, and indicate if changes were made. You may do so in any reasonable manner, but not in any way that suggests the licensor endorses you or your use.
-
ShareAlike — If you remix, transform, or build upon the material, you must distribute your contributions under the same license as the original.
- No additional restrictions — You may not apply legal terms or technological measures that legally restrict others from doing anything the license permits.
References
- Agritama, R., Huda, M., & Setiyo Rini, T. (2018). "Faktor-Faktor Yang Mempengaruhi Keterlambatan Proyek Konstruksi Di Surabaya". Jurnal Rekayasa Dan Manajemen Konstruksi, 6(1), 25–32.
- anna margareta andreana malir, dirani sudarwadi, y heri saptomo. (2018). Faktor - faktor Penyebab Keterlambatan Pelaksanaan Pekerjaan Proyek Kontruksi di Kabupate Manokwari. Cakrawala, 1.
- Aziz, R. F. (2013). Ranking of delay factors in construction projects after Egyptian revolution. Alexandria Engineering Journal, 52(3), 387–406. https://doi.org/10.1016/j.aej.2013.03.002
- Bakhtiyar, A., Soehardjono, A., & Hasyim, M. H. (2012). Analisis faktor-faktor yang mempengaruhi keterlambatan proyek konstruksi pembangunan gedung di kota lamongan. Jurnal Rekayasa Teknik Sipil, 6(1), 55–66.
- Delays, T. H. E., In, F., The, F., Constructions, B., & Region, K. (2019). Faktor-Faktor Penyebab Keterlambatan Penyelesaian Proyek Gedung Di Kabupaten Karangasem. Jurnal Ilmiah Teknik Sipil, 79–87.
- Hassan, H., Mangare, J. B., & Pratasis, P. A. K. (2016). Faktor-faktor penyebab keterlambatan pada proyek konstruksi dan alternatif penyelesaiannya (studi kasus : di manado town square III). Jurnal Sipil Statik Vol.4, 4(11), 657–664.
- Mahapatni, I. A. P. S. (2019). Metode Perencanaan dan Pengendalian Proyek Konstruksi. In UNHI Press.
- Molwus, J. J. (2014). Stakeholder management in construction projects: a life cycle based framework. Thesis. http://www.ros.hw.ac.uk/bitstream/handle/10399/2877/MolwusJJ_1014_sbe.pdf?sequence=1
- Proboyo, B. (1999). Keterlambatan Waktu Pelaksanaan Proyek : Klasifikasi dan Peringkat dari Penyebab-penyebabnya (Project Implementation Delay : Causes Classification and Ratings). Dimensi Teknik Sipil, 1(1), 49–58.
- Putra Agritama, R., Huda, M., & Setiyo Rini, T. (2018). Faktor-Faktor Yang Mempengaruhi Keterlambatan Proyek Konstruksi Di Surabaya. Jurnal Rekayasa Dan Manajemen Konstruksi, 6(1), 25–32.
- Rajablu, M., Marthandan, G., & Yusoff, W. F. W. (2014). Managing for stakeholders: The role of stakeholder-based management in project success. Asian Social Science, 11(3), 111–125. https://doi.org/10.5539/ass.v11n3p111
- Rantepasang, E. I. (2015). Pelaksanaan Proyek Di Sorong – Papua Barat.
- Sugiyono. 2003. Metode Penelitian. Bandung: Alfabeta.
- Sugiyono (2019). Statistika untuk Penelitian. Bandung : CV Alfabeta.
- Wirabakti, D. M., Abdullah, R., & Maddeppungeng, A. (2014). Studi Faktor-Faktor Penyebab Keterlambatan Proyek Konstruksi Bangunan Gedung. Teknik Sipil Universitas Agung Tirtayasa, Vol. 6, 15–29.
References
Agritama, R., Huda, M., & Setiyo Rini, T. (2018). "Faktor-Faktor Yang Mempengaruhi Keterlambatan Proyek Konstruksi Di Surabaya". Jurnal Rekayasa Dan Manajemen Konstruksi, 6(1), 25–32.
anna margareta andreana malir, dirani sudarwadi, y heri saptomo. (2018). Faktor - faktor Penyebab Keterlambatan Pelaksanaan Pekerjaan Proyek Kontruksi di Kabupate Manokwari. Cakrawala, 1.
Aziz, R. F. (2013). Ranking of delay factors in construction projects after Egyptian revolution. Alexandria Engineering Journal, 52(3), 387–406. https://doi.org/10.1016/j.aej.2013.03.002
Bakhtiyar, A., Soehardjono, A., & Hasyim, M. H. (2012). Analisis faktor-faktor yang mempengaruhi keterlambatan proyek konstruksi pembangunan gedung di kota lamongan. Jurnal Rekayasa Teknik Sipil, 6(1), 55–66.
Delays, T. H. E., In, F., The, F., Constructions, B., & Region, K. (2019). Faktor-Faktor Penyebab Keterlambatan Penyelesaian Proyek Gedung Di Kabupaten Karangasem. Jurnal Ilmiah Teknik Sipil, 79–87.
Hassan, H., Mangare, J. B., & Pratasis, P. A. K. (2016). Faktor-faktor penyebab keterlambatan pada proyek konstruksi dan alternatif penyelesaiannya (studi kasus : di manado town square III). Jurnal Sipil Statik Vol.4, 4(11), 657–664.
Mahapatni, I. A. P. S. (2019). Metode Perencanaan dan Pengendalian Proyek Konstruksi. In UNHI Press.
Molwus, J. J. (2014). Stakeholder management in construction projects: a life cycle based framework. Thesis. http://www.ros.hw.ac.uk/bitstream/handle/10399/2877/MolwusJJ_1014_sbe.pdf?sequence=1
Proboyo, B. (1999). Keterlambatan Waktu Pelaksanaan Proyek : Klasifikasi dan Peringkat dari Penyebab-penyebabnya (Project Implementation Delay : Causes Classification and Ratings). Dimensi Teknik Sipil, 1(1), 49–58.
Putra Agritama, R., Huda, M., & Setiyo Rini, T. (2018). Faktor-Faktor Yang Mempengaruhi Keterlambatan Proyek Konstruksi Di Surabaya. Jurnal Rekayasa Dan Manajemen Konstruksi, 6(1), 25–32.
Rajablu, M., Marthandan, G., & Yusoff, W. F. W. (2014). Managing for stakeholders: The role of stakeholder-based management in project success. Asian Social Science, 11(3), 111–125. https://doi.org/10.5539/ass.v11n3p111
Rantepasang, E. I. (2015). Pelaksanaan Proyek Di Sorong – Papua Barat.
Sugiyono. 2003. Metode Penelitian. Bandung: Alfabeta.
Sugiyono (2019). Statistika untuk Penelitian. Bandung : CV Alfabeta.
Wirabakti, D. M., Abdullah, R., & Maddeppungeng, A. (2014). Studi Faktor-Faktor Penyebab Keterlambatan Proyek Konstruksi Bangunan Gedung. Teknik Sipil Universitas Agung Tirtayasa, Vol. 6, 15–29.